10. ESTUDIO FINANCIERO
10.1. INVERSIONES
INVERSION TOTAL DEL PROYECTO
RUBROS | CANTIDAD | COSTO UNITARIO | CONTRAPARTIDA ASOCIACION | FINANCIAMIENTO | TOTAL | ||
APORTES |
|
| 50,000.00 |
| 50,000.00 | ||
APORTE DE LA EMPRESA EN DINERO | 1 | 50,000.00 | 50,000.00 |
| 50,000.00 | ||
BIENES |
|
|
|
| |||
BIENES DE LA EMPRESA |
|
| 230,000.00 |
| 230,000.00 | ||
CAMIONETAS MARCA TOYOT HYLUX | 1 | 90,000.00 | 90,000.00 |
| 90,000.00 | ||
SALA DE INCUBACIÓN ARTESANAL | 1 | 20,000.00 | 20,000.00 |
| 20,000.00 | ||
VIVIENDA Y OFICINA | 1 | 50,000.00 | 50,000.00 |
| 50,000.00 | ||
TERRENO PARA LA SALA INCUBACIÓN | 1 | 20,000.00 | 20,000.00 |
| 20,000.00 | ||
TERRENO YURA PARA LA PLANTA DE ALIMENTOS | 1 | 50,000.00 | 50,000.00 |
| 50,000.00 | ||
INFRAESTRUCTURAS |
|
| 174061.03 |
| 174,061.03 | ||
OBRAS PRELIMINARES | 1 | 11025.21 | 11025.21 |
| 11025.21 | ||
SISTEMA DE CAPTACIÓN | 1 | 23490.53 | 23490.53 |
| 23490.53 | ||
LINEA DE CONDUCCIÓN | 1 | 9166.47 | 9166.47 |
| 9166.47 | ||
SALA DE ALEVINAJE | 2 | 36355.19 | 72710.38 |
| 72710.38 | ||
ALMACEN Y GUARDIANIA | 1 | 14051.27 | 14051.27 |
| 14051.27 | ||
SISTEMA ELÉCTRICO | 1 | 12192.47 | 12192.47 |
| 12192.47 | ||
INSTALACIONES SANITARIAS | 1 | 5999.99 | 5999.99 |
| 5999.99 | ||
TRANSPORTE | 1 | 4800 | 4800 |
| 4800 | ||
MEDIO AMBIENTE | 1 | 599.99 | 599.99 |
| 599.99 | ||
GASTOS GENERALES 13% | 1 | 20024.72 | 20024.72 |
| 20024.72 | ||
INSUMOS |
|
|
| 145,737.96 | 145,737.96 | ||
ALIMENTO PARA TRUCHAS (KG) | 17448 | 4.02 |
| 70,140.96 | 70,140.96 | ||
100 MILARES OVAS DE TRUCHA ARCO IRIS | 100 | 99.47 |
| 9,947.00 | 9,947.00 | ||
MODULO BÁSICO DE JALUAS FLOTANTES 4 JAULAS DE 7X7M | 1 | 65,650.00 |
| 65,650.00 | 65,650.00 | ||
EQUIPOS PLANTA DE ALIMENTOS |
|
|
| 139,475.00 | 139,475.00 | ||
MOLINO DE MARTILLO MV35-45C | 1 | 11,000.00 |
| 11,000.00 | 11,000.00 | ||
MEZCLADORA HORIZONTAL MHV 200-I/C | 1 | 10,000.00 |
| 10,000.00 | 10,000.00 | ||
EXTRUSORA EV-50-I/C | 1 | 65,975.00 |
| 65,975.00 | 65,975.00 | ||
ELEVADOR DE CHEVRONES ECHV-I/C | 1 | 11,500.00 |
| 11,500.00 | 11,500.00 | ||
SECADORA ROTATIVA HORIZONTAL | 1 | 24,000.00 |
| 24,000.00 | 24,000.00 | ||
ENFRIADORA EPV-I/C | 1 | 17,000.00 |
| 17,000.00 | 17,000.00 | ||
EQUIPOS SALA DE INCUBACIÓN |
|
|
| 77,000.00 | 77,000.00 | ||
TANQUE DE FIBRA DE VIDRIO CON 6 BASTIDORES CADA UNO | 14 | 5,500.00 |
| 77,000.00 | 77,000.00 | ||
SERVICIOS |
|
|
| 121,800.00 | 121,800.00 | ||
CONSULTOR EXTERNO | 8 | 3,000.00 |
| 24,000.00 | 24,000.00 | ||
JEFE DE PRODUCCIÓN (MES) | 12 | 4,000.00 |
| 48,000.00 | 48,000.00 | ||
ASISTENTE DE PRODUCCIÓN(MES) | 12 | 2,000.00 |
| 24,000.00 | 24,000.00 | ||
ADMINISTRADOR GENERAl(MES) | 12 | 2,000.00 |
| 24,000.00 | 24,000.00 | ||
UTILES DE OFICINA | 1 | 1,800.00 |
| 1,800.00 | 1,800.00 | ||
MANO DE OBRA |
|
| 40,800.00 |
| 40,800.00 | ||
OBREROS EN PLANTA (MES) | 24 | 1,200.00 | 28,800.00 |
| 28,800.00 | ||
GUARDIANES(MES) | 12 | 1,000.00 | 12,000.00 |
| 12,000.00 | ||
CAPACITACIONES |
|
|
| 14,000.00 | 14,000.00 | ||
CAPACITACIÓN EN LA CRIANZA DE ALEVINOS | 4 | 2,000.00 |
| 8,000.00 | 8,000.00 | ||
CAPACITACIONES EN MANEJO DE OVAS | 3 | 2,000.00 |
| 6,000.00 | 6,000.00 | ||
|
|
|
|
| 494,861.03 | 498,012.96 | 992,873.99 |
|
|
| |||||
| 49.84% | 50.16% | 100.00% | ||||
El consultor externo sus servicios son de 8 meses por 15 días cada mes en aspectos puntuales.
La inversión total del proyecto es de S/. 992,873.99 nuevos soles, para ser invertidos en el proyecto siendo el monto cofinanciado de la Empresa Piscis Pabellones S.R.L. la suma de S/. 494,861.03 y el monto cofinanciado por un inverisionista de S/. 498,012.96.96.
...